Friday, Sept. 17, 2021

Natural gas line installation is complete for this year, and County Road B has been reopened between Albemarle Court and Lexington Avenue. We will perform line testing procedures and restoration through October.

During the coming week, construction will occur in the following areas:

  • County Road B, between Rice Street and Albemarle Court.
    • Testing activities.
    • One-way traffic on County Road B, from Rice Street to Albemarle Court.
    • Temporary sidewalk in place.
  • County Road B, between Victoria Street and Lexington Avenue.
    • Restoration.
  • County Road B, between Lexington Avenue and Lexington Park parking lot.
    • Testing activities.
    • Shifting lanes.
    • Crosswalk closure.
  • County Road B, between Lexington and Hamline avenues.
    • Marking of utility lines and utility survey holes.
    • Short-term, shifting lane closures.
  • Hamline Avenue, between County Road B and County Road C.
    • Marking of utility lines and utility survey holes.
    • Short-term, shifting lane closures.

Construction schedules are subject to change.


Friday, Sept. 10, 2021

During the coming week, construction will occur in the following areas:

  • County Road B, between Rice Street and Albemarle Court.
    • Testing activities.
    • One-way traffic on County Road B, from Rice Street to Albemarle Court.
    • Temporary sidewalk in place.
  • County Road B, between Cohansey Boulevard and Dale Street.
    • Restoration.
  • County Road B, between Dale and Victoria streets.
    • Restoration.
    • Follow posted detours.
    • Short-term driveway closures.
  • Intersection of County Road B and Victoria Street.
    • Restoration.
    • Victoria Street closed to through traffic.
  • County Road B, between Victoria Street and Lexington Avenue.
    • Line installation.
    • One-way traffic on County Road B, from Victoria Street to Lexington Avenue.
    • Follow posted detours.
    • Short-term driveway closures.
  • County Road B, between Lexington Avenue and Lexington Park parking lot.
    • Testing activities.
    • Shifting lanes.
    • Crosswalk closure.

Construction schedules are subject to change.


Friday, Sept. 3, 2021

In observance of Labor Day, crews will not work Sunday, Sept. 5, 2021, and Monday, Sept. 6, 2021. Construction will resume on Tuesday, Sept. 7, 2021.

During the coming week, construction will occur in the following areas:

  • County Road B, between Rice Street and Albemarle Court.
    • Testing activities.
    • One-way traffic on County Road B from Rice Street toward Albemarle Court.
    • Temporary sidewalk in place.
  • County Road B, between Cohansey Boulevard and Dale Street.
    • Restoration activities.
    • Crews will return later this year for permanent restoration.
  • County Road B, between Dale and Victoria streets.
    • Restoration activities.
    • Follow posted detours.
    • Short-term driveway closures.
  • Intersection of County Road B and Victoria Street.
    • Restoration activities.
    • Victoria Street closed to through traffic starting Tuesday, Sept. 7, 2021.
  • County Road B, between Victoria Street and Lexington Avenue.
    • Line installation.
    • One-way traffic on County Road B from Victoria Street toward Lexington Avenue.
    • Follow posted detours.
    • Short-term driveway closures.
  • County Road B, between Lexington Avenue and Lexington Park parking lot.
    • Testing activities.
    • Shifting lanes.
    • Crosswalk closure.

Construction schedules are subject to change.