Schedule

The following schedule for the Northeast Metro Natural Gas Project has been established and 2019 construction has been completed. Please note that the project schedule is subject to change

  • 2018: Project need identified.
  • 2018 through spring 2020: Project permitting and engineering.
  • May 2019: Begin Phase 1 construction.
  • November 2019: Complete Phase 1 construction.
  • Spring 2020: Begin Phase 2 construction.
  • Fall 2020: Complete Phase 2 construction.
  • Fall 2020: Project in-service.